October 15, 2026
Burlingame's Broadway rail crossing is ranked as the highest-priority grade separation project in California, and it has been studied for more than a decade. Today it sits at 65% design, with a total estimated cost of $662 million. Most people who look at homes near Broadway and California Drive know a project is coming. Fewer know that most of the money for the later phases depends on one federal decision. That decision has no set date, but it could come in November or December 2026.
Design work is moving ahead in the meantime. Property acquisition, early work and a four-year construction window are funded through a plan built on that grant. If you're comparing Burlingame neighborhoods, the date to watch is in the next few months, well before any finished crossing.
In March 2025, the Burlingame City Council reviewed ways to cut costs and agreed to move forward with a design that has no Broadway station. The project now focuses only on separating the tracks from the road.
Today Broadway is Caltrain's only weekend-only station, according to the agency's FY2026 Annual Ridership Report, which covers July 2025 through June 2026. Weekend use is growing. Caltrain estimates Broadway averaged 126 weekend-origin trips per day in FY2026, up 38% from 91 in FY2025. The report notes that its model is based on fare-media sales, not full passenger counts. On the timetable, Burlingame station is the next stop north and Millbrae the next stop south.
The Broadway business district has argued for more rail service, not less. In June 2025, the Burlingame Voice reported that Broadway BID president John Kevranian said restoring weekday service would help the district, and that more than 2,000 people used the station each week before weekday service ended. That figure is an advocacy claim from that time, not a current ridership estimate. The design now moving forward doesn't include a station.
That leaves construction timing as the open question for a buyer near Broadway.
At the Burlingame City Council meeting on August 17, 2026, Caltrain deputy executive director Sherry Bullock walked through the schedule. The San Mateo Daily Journal reported it this way:
| Phase | Timing reported | What it involves |
|---|---|---|
| 65% design | Package submitted May 29, 2026 | Plans, draft geotechnical report, outstanding design items |
| Federal grant decision | Possibly November or December 2026, no set date | $90.5 million Railroad Crossing Elimination grant |
| Final design | Planned to finish by 2027 | Moving from 65% to 100% design |
| Property acquisition and early work | 2027 and 2028 | Acquiring property around the crossing, pre-construction work, community information sessions |
| Construction | Four years, estimated 2029 to 2032 | Separating the road from the tracks |
Caltrain's own project page gives a slightly different start date. It says construction "could begin as soon as November 2028, subject to funding availability." The two dates may reflect different schedule assumptions. Either way, a 2028 or 2029 start is about two years away. A buyer who closes in 2027 would likely spend the property acquisition years living nearby and could still be in the home when construction begins.
The cost estimate includes $25.8 million for real estate acquisition, plus $63.2 million for design, $484 million for construction and $73.8 million in contingency. The materials we reviewed don't say which parcels are involved. SMCTA's report lists "ROW Strategy: Meet with the Real Estate team" as future work.
The current funding plan depends on the pending $90.5 million federal grant. If it's approved, the San Mateo County Transportation Authority's share grows by $321.6 million and the City of Burlingame adds another $9.6 million. Those local amounts depend on the federal award. If the grant doesn't come, most of the funding plan doesn't either.
Mayor Michael Brownrigg was direct about that possibility. The Daily Journal reported his comment: "If the [railroad crossing elimination] grant doesn't come through, then we need to have a really deep conversation about what's next. Costs are going to keep going up the longer this takes, we're just going to be chasing a dream."
Even if the grant comes through, the Daily Journal reported that the estimate still faces an $89.7 million gap. At the same meeting, Councilmember Colson said that if the project is short only a fairly small amount, such as the contingency, it could keep moving and sort out the rest later. She also said projects that are ready to build tend to attract more funding.
SMCTA's September 3, 2026 board minutes summarize the executive director's report as "Restoration of $70 million in state funding." That $70 million was already part of the funding plan. The city's August 17 funding table already lists the $70 million as a CalSTA TIRCP construction source, next to $15 million from the CPUC's Section 190 program, and the $89.7 million gap was calculated with both included.
The money has been at risk before. In a May 29, 2024 release, State Senator Josh Becker said Burlingame's $70 million award was among the TIRCP awards left out of the Governor's proposed 2024–25 budget. His June 27, 2024 release said the final budget restored TIRCP funding for previously approved priority projects, including Burlingame. The project already had that money. It doesn't change the gap.
The agencies haven't waited for the federal decision. They've kept funding design work, on the idea City Manager Lisa Goldman described in the Daily Journal's August coverage: "early money begets later money." The record since August:
The federal side has been quiet. The FRA's Railroad Crossing Elimination program page lists the FY2025–26 funding notice but no list of recipients for that round, and it was last updated June 9, 2026. Burlingame submitted its application on June 8, 2026. As of October 12, 2026, we haven't found an announcement that the grant was awarded or denied.
A buyer near the crossing will want answers the current documents don't give. SMCTA's third-quarter report lists closure staging and detour analysis for Broadway as work still in progress, not a finished traffic plan. None of the sources we reviewed says how long Broadway would be closed at the tracks, where detours would go, or how construction would affect Broadway merchants or California Drive.
Dropping the temporary "shoofly" tracks from the plan matters here too. Those tracks would have carried trains around the work zone. Removing them was one of the cost-saving changes that came with dropping the station. How the work is staged without them is part of the analysis still underway.
The finished design is easier to describe. It keeps bicycle and pedestrian access along Broadway and adds new pedestrian underpasses beneath the tracks at Cadillac Way and Sanchez Avenue, connected to a set of walking and biking improvements. For streets near those two underpasses, the long-term change is more ways to cross the tracks on foot. The short-term change depends on staging details that haven't been released.
Will Broadway station reopen for weekday service after construction? Not under the current plan. The design the City Council chose in March 2025 and Caltrain carried to 65% doesn't include a Broadway station.
When would construction start? Caltrain's project page says as soon as November 2028, depending on funding. Caltrain's August update to the city described a four-year construction window from 2029 to 2032.
Is the project fully funded? No. Even if the $90.5 million federal grant is awarded and the conditional local money follows, the August estimate leaves an $89.7 million gap. The estimate will be updated again at 95% design.
If you're looking at homes near Broadway, the two of us can follow each step of this project with you, from the federal grant decision this winter through the property acquisition years and the staging plans that will eventually show what construction looks like on your block. To talk through how this timeline lines up with your own move, reach out to Rachel & Sarah and request a Concierge Home Consultation.
Stay up to date on the latest real estate trends.
We pride ourselves in providing personalized solutions that bring our clients closer to their dream properties and enhance their long-term wealth.